Waterfall vs Scrum on a fixed date and a fixed budget

The contract says July 2. The budget says 800 person-days. The team wants to work in sprints. None of that is a contradiction - it only looks like one while everybody also pretends the scope is fixed. This page shows how to take a project with an end date and a budget, lay its whole scope out across iterations, and still keep the part of Scrum that makes it worth doing: the right to change your mind about what gets built.

Last updated · about 13 minutes

The short answer

A fixed date and a fixed budget fix the capacity, not the scope. Divide the time into sprints and the money into team-sprints, and you know how much work fits. Break the full scope into a sized tree, rank it, and fill the sprints from the top.

Scrum keeps the date and the cost still and lets the scope move. That is exactly the shape a fixed-date project already has, once nobody insists the scope is fixed as well.

The rest of this page is the mechanics: how to get from a deadline and a budget to a number of sprints, how to break a whole project down so it can be ranked, how to place it across iterations without freezing it, and what to put in the contract so the flexibility survives the first steering committee.

What actually differs

Waterfall and Scrum are usually compared as philosophies. For a project with a deadline it is more useful to compare them as answers to six practical questions.

QuestionWaterfallScrum
What is fixed?Scope, then date and cost are derived from itDate and cost, and scope is ranked to fit
When is the estimate made?Once, before the build, as a priceUp front as a forecast, then corrected every sprint
How is change handled?A change request that moves the date or the priceA swap in the backlog that moves something else out
When does anything work?At the end, after integration and testingAt the end of every sprint, in small slices
When is risk discovered?Late, usually in system testingEarly, because the risky slice is built first
What does the sponsor watch?Phase gates and percent completeWorking increments and a burn-up chart

Read down the Scrum column and notice what is missing: nothing in it says the scope is unknown. A Scrum project with a deadline still needs the whole scope written down and sized. What changes is the status of that list. In waterfall it is a promise. In Scrum it is a forecast, ranked so that whatever does not fit falls off the bottom rather than out of the middle.

The triangle: something has to move

Every project has the same three dials - date, cost and scope - and quality hiding underneath them. Fix all three and the project still moves, it just moves through the one dial nobody wrote down: corners get cut in testing, the team works weekends, and the defects arrive after go-live.

The rule of thumb

Fix two, flex one, and say out loud which one. A fixed-date, fixed-budget project has already chosen: the scope is the dial. Waterfall flexes the date and the cost through change requests. Scrum flexes the scope through the backlog. Pretending to fix all three is the most common way a project ends up flexing quality instead.

This is not an argument for building less. Most projects that run this way deliver everything that mattered, because the ranking puts the things that matter at the top and the last few sprints are spent on what turned out to be important rather than on what was guessed to be important a year earlier.

Step 1: turn the date and the budget into capacity

Start with the two numbers you were given, and turn each one into sprints.

  1. Count the sprints the calendar allows. Take the working weeks between the start and the go-live date, subtract what is not development - a short setup sprint at the front, a stabilization sprint at the end, public holidays and the weeks the team is known to be away - and divide by the sprint length.
  2. Count the sprints the money allows. Price one sprint of the whole team: people times working days per sprint times the day rate. Divide the budget, minus any fixed costs such as licenses or hosting, by that number.
  3. Take the smaller of the two. That is the capacity of the project. If the money buys more sprints than the calendar has, you can add people, but only up to the point a team can absorb them. If the calendar has more sprints than the money, the date is not the real constraint and somebody should know that now.
A worked example

Start on January 4, go live on July 2: twenty-six working weeks. One setup sprint, one stabilization sprint and two weeks of holidays leave ten delivery sprints of two weeks. A team of six at ten working days a sprint is 60 person-days a sprint, so the ten sprints cost 600 person-days of delivery, plus 120 for the setup and stabilization sprints. The budget of 800 person-days covers that with 80 to spare. The calendar is the binding constraint, and the 80 become the risk reserve.

Person-days are not the same as output. A team of six does not finish 60 person-days of estimated work in a sprint, because meetings, reviews and the work nobody estimated eat into it. That is why the next steps measure the scope in the same unit the team will later be measured in, and why the first sprints exist partly to find out what that unit is worth.

Step 2: break the whole scope down

A backlog that has only the next two sprints in it cannot answer the sponsor's one real question, which is whether July 2 is going to happen. So the whole scope gets written down once, at the start, as a work breakdown structure: the product at the top, then epics, then features, then stories small enough to finish inside a sprint.

The trick that keeps this from turning into a waterfall specification is uneven depth. Break the first two or three sprints' worth of work down to stories. Break the middle of the project down to features. Leave the far end as epics with a rough size. Detail written for work that is five months away is mostly wrong by the time you get there, and keeping it shallow is what lets it change cheaply.

  1. 1Customer portal–92 pts
    1. 1.1Accounts and sign-in–19 pts
      1. 1.1.1Register with emailS3 pts
      2. 1.1.2Single sign-on with the company directoryL8 pts
      3. 1.1.3Reset a forgotten passwordS3 pts
      4. 1.1.4Roles and permissionsM5 pts
    2. 1.2Orders and invoices–31 pts
      1. 1.2.1Order historyM5 pts
      2. 1.2.2Invoice downloadM5 pts
      3. 1.2.3ERP integrationXL21 pts
    3. 1.3Support tickets (epic, not yet split)XL21 pts
    4. 1.4Reporting dashboard (epic, not yet split)XL21 pts
An excerpt of one backlog, at uneven depth on purpose. The first branches are split into stories because they are built first. The last two are still one row each with a rough size, and they will be split when they get close. Every parent is the sum of what is under it.

Size the rows the way the team will be asked to size them later. Story points or t-shirt sizes are fine as long as one person on the plan side converts them into time and money, and as long as the epics at the far end are sized with the same scale rather than in a different unit nobody can compare.

Step 3: hold the scope against the capacity

Now there are two numbers in the same unit: what the project contains, and what the sprints can hold. To compare them you need one more number, the team's velocity - how many points a sprint actually finishes.

If the team has worked together on similar work, take the average of its last few sprints. If it has not, forecast it: plan one sprint's worth of stories the way the team would, count the points, and treat that as a guess to be replaced after sprint two. Either way, use a range rather than a single number. Ten sprints at 18 to 24 points is a capacity of 180 to 240 points, and that range is the honest answer to "will it fit?".

Then rank the scope. The simplest scheme that holds up in front of a sponsor is MoSCoW: must have, should have, could have, won't have this time. Two rules make it useful rather than decorative.

Step 4: lay the scope across the sprints

A release plan is the ranked backlog cut into sprint-sized slices, with a goal for each slice. It is the document that replaces the waterfall Gantt chart, and it should fit on one page. Four principles decide the order.

SprintGoalDetail levelMilestone
0Environments, pipeline, backlog sized, team agreementsTasks
1Walking skeleton: sign in, one page, deployedStories
2ERP integration spike and first real order dataStoriesVelocity known
3 – 4Accounts, roles, orders and invoicesFeatures
5Remaining must-haves, first user testingFeaturesMinimum viable release
6 – 8Support tickets and the should-havesEpics
9 – 10Reporting and the could-haves that still fitEpicsFeature complete
11Stabilization, acceptance testing, data migrationTasksGo-live

Notice the third column. The plan is detailed where it is about to happen and coarse where it is far away. It still covers the whole scope, so it can answer the date question, but it does not commit anybody to the wording of a story that will not be written until June.

Step 5: keep it flexible

A release plan made once and defended for six months is a waterfall plan in a sprint costume. Four habits keep it a Scrum plan.

Plan in rolling waves

At every sprint planning, split the next two sprints' worth of features into stories. At every review, look one level further out and split whatever epic has come close enough. The tree grows downward just ahead of the team, which is the only place detail is worth paying for.

Swap, do not add

New ideas are welcome at any time, as long as they come with a question: what moves out to make room? A new item of similar size swaps with something below the line, and the date and the cost do not move. This single rule is what lets a sponsor change their mind without a change request, and it is the reason a fixed-date Scrum project can absorb learning that would derail a waterfall one.

Re-forecast every sprint

After every sprint, replace the guessed velocity with the measured one and redraw the line. The question "what will we have on July 2?" gets a fresh answer every two weeks, based on evidence rather than on the optimism of month one. A forecast that changes is not a failure. A forecast that never changes is one nobody is checking.

Spend the reserve on purpose

Keep the risk reserve from step 1 visible as its own row, and decide in advance who may spend it and on what. A reserve that is quietly absorbed into every estimate disappears without anybody noticing. One that sits on the plan as a number gets spent when something real happens, and its size tells the sponsor how much trouble the project can still take.

Tracking: one chart for the sponsor

A burn-down chart shows remaining work, which hides the most important event on a flexible project: scope being added. Use a burn-up chart instead. It has two lines - work completed, rising sprint by sprint, and total scope, which rises when something is added and falls when something is cut.

Where the completed line is heading relative to the scope line, extended to the deadline with the best and worst velocity, is the whole status report. If the must-have line is crossed well before the date, the project is healthy. If the projected completed line does not reach the must-haves by the date, it is time for a conversation about scope, and the chart shows exactly how much needs to move.

The contract that makes it work

Most fixed-price IT contracts are written for waterfall: a specification, a price and a change request procedure. Running Scrum under one means every swap becomes a negotiation. Three clauses make the contract match the method.

None of this needs a lawyer who loves agile. It needs both sides to agree that the scope was never really fixed, and to write the contract around the two things that were.

What stays waterfall

Not everything in an IT project can be cut into sprints, and pretending otherwise causes as much trouble as forcing everything into phases. Some work is sequential by nature: signing a contract with a vendor, a security audit with a fixed slot, a data migration that runs once over a weekend, a hardware delivery, training two hundred users the week before go-live.

Put those items on the same plan as fixed milestones with dates, outside the sprint backlog, and let the sprints feed them. The software is built in increments. The launch is still an event, and an event has a date. A plan that shows both - sprints for the build, milestones for the things the build depends on - is what most real fixed-date projects end up looking like, whatever they are called.

Common mistakes

Do

  • Turn the date and the budget into a number of sprints before anything else.
  • Write the whole scope down at the start, at uneven depth.
  • Rank the scope and keep the must-haves well inside the low capacity.
  • Build a walking skeleton first and the riskiest integration second.
  • Re-forecast every sprint with the measured velocity.
  • Swap equal sizes instead of adding scope.
  • Report with a burn-up chart that shows the scope line moving.

Don't

  • Promise the full scope, the date and the budget all at once.
  • Plan only the next two sprints and hope the rest fits.
  • Split work five months away into stories nobody will recognize.
  • Treat the should-haves as commitments in disguise.
  • Hide the risk reserve inside every estimate.
  • Leave testing and migration for a phase after the last sprint.
  • Use a burn-down chart that cannot show scope being added.

The expensive mistake is the first one. A project that commits to everything has no dial left to turn when reality arrives, so it turns the one nobody can see. Choosing the dial at the start is the single decision that makes the rest of this page possible.

Frequently asked questions

Can you use Scrum on a project with a fixed deadline and a fixed budget?

Yes, and it fits better than it looks. A fixed date and a fixed budget fix the capacity of the project, which is the number of sprints the team can work. Scrum already keeps time and cost still and lets the scope move, so the only thing that has to change is the assumption that the scope is fixed too. Write the full scope down, rank it, and fill the sprints from the top, with the must-haves well inside what the team can deliver.

What is the main difference between waterfall and Scrum?

Waterfall fixes the scope first and derives the date and the cost from it, so change arrives as a change request that moves the date or the price. Scrum fixes the date and the cost of each sprint and ranks the scope to fit, so change arrives as a swap in the backlog that moves something else out. Waterfall delivers working software at the end. Scrum delivers a working increment every sprint, which is also why it finds risk earlier.

How do you plan the full scope of a project across sprints?

Turn the date and the budget into a number of sprints, then break the whole scope down into a tree of epics, features and stories at uneven depth: detailed for the next few sprints and coarse for the far end. Size it, rank it with MoSCoW, and compare it with the team's velocity as a range. Then cut the ranked list into sprint-sized slices with a goal each, building a walking skeleton first and the riskiest integration next.

How do you keep Scrum flexible on a fixed-price contract?

Write the contract around the prioritized backlog rather than a frozen specification. The price buys the capacity of the agreed sprints, the must-haves are guaranteed, and the customer may swap any item that has not been started for a new one of equal size at no cost. An optional early-exit clause lets the customer stop when what has been built is enough, paying a share of the remaining budget.

How many sprints do I need before a deadline?

Count the working weeks between the start and the go-live date, subtract a setup sprint at the front, a stabilization sprint at the end and any holidays, and divide by the sprint length. Then check what the budget buys by dividing it by the cost of one sprint of the whole team. The smaller of the two numbers is the capacity of the project.

Should I use a burn-down or a burn-up chart on a fixed-date project?

A burn-up chart. A burn-down chart shows only remaining work, so scope being added looks like the team slowing down. A burn-up chart has one line for completed work and one for total scope, so you can see both the progress and every change to the plan, and extend the completed line to the deadline to see what will be done by then.

Break the scope down before the first sprint